APTITUDE QUIZ
Q1.A can do a piece of work in 10 days, B in 15 days. They work together for 5 days, the rest of the work is finished by C in two more days. If they get Rs. 3000 as wages for the whole work, what are the daily wages of A, B and C respectively (in Rs)
- A) 200, 250, 300
- B) 300, 200, 250
- C) 200, 300, 400
- D) None of these
Q2.12 men can complete a work in 8 days. 16 women can complete the same work in 12 days. 8 men and 8 women started working and worked for 6 days. How many more men are to be added to complete the remaining work in 1 day
- A) 8
- B) 12
- C) 16
- D) 24
Q3.A, B and C can do a piece of work in 24 days, 30 days and 40 days respectively. They began the work together but C left 4 days before the completion of the work. In how many days was the work completed
- A) 11 days
- B) 12 days
- C) 13 days
- D) 14 days
Q4.A can do a certain work in the same time in which B and C together can do it.If A and B together could do it in 20 days and C alone in 60 days ,then B alone could do it in
- A) 20days
- B) 40 days
- C) 50 days
- D) 60 days
Q5.P can complete a work in 12 days working 8 hours a day.Q can complete the same work in 8 days working 10 hours a day. If both p and Q work together,working 8 hours a day,in how many days can they complete the work
- A) 6011
- B) 6111
- C) 7111
- D) 7211
Q6.A works twice as fast as B.If B can complete a work in 18 days independently,the number of days in which A and B can together finish the work is
- A) 4 days
- B) 6 days
- C) 8 days
- D) 10 days
Q7.A Contractor employed a certain number of workers to finish constructing a road in a certain scheduled time. Sometime later, when a part of work had been completed, he realised that the work would get delayed by three-fourth of the scheduled time, so he at once doubled the no of workers and thus he managed to finish the road on the scheduled time. How much work he had been completed, before increasing the number of workers
- A) 10 %
- B) 14 27 %
- C) 20 %
- D) Can’t be determined
Q8.A group of workers was put on a job. From the second day onwards, one worker was withdrawn each day. The job was finished when the last worker was withdrawn. Had no worker been withdrawn at any stage, the group would have finished the job in 55% of the time. How many workers were there in the group
- A) 50
- B) 40
- C) 45
- D) 10
Q9.A is thrice efficient as B and C is twice as efficient as B. what is the ratio of number of days taken by A,B and C, when they work individually
- A) 263
- B) 236
- C) 123
- D) 312
Q10.(x-2) men can do a piece of work in x days and (x+7) men can do 75% of the same work in (x-10)days. Then in how many days can (x+10) men finish the work
- A) 27 days
- B) 12 days
- C) 25 days
- D) 18 days
Q11.A and B can do a piece of work in 30 days , while B and C can do the same work in 24 days and C and A in 20 days . They all work together for 10 days when B and C leave. How many days more will A take to finish the work
- A) 18 days
- B) 24 days
- C) 30 days
- D) 36 days
Q12.The ratio of efficiency of A is to C is 53. The ratio of number of days taken by B is to C is 23. A takes 6 days less than C, when A and C completes the work individually. B and C started the work and left after 2 days. The number of days taken by A to finish the remaining work is
- A) 4.5
- B) 5
- C) 6
- D) 9 13
Q13.A, B and C can complete a piece of work in 24,6 and 12 days respectively.Working together, they will complete the same work in
- A) 124 days
- B) 724 days
- C) 247 days
- D) 4 days
Q14.Pipe A can fill the tank in 4 hours,while pipe B can fill it in 6 hours working separately.pipe C can empty whole the tank in 4 hours. He opened the pipe A and B simultaneously to fill the empty tank. He wanted to adjust his alarm so that he could open the pipe C when it was half-filled, but he mistakenly adjusted his alarm at a time when his tank would be 34th filled. what is the time difference between both the cases, to fill the tank fully
- A) 48 min
- B) 54 min
- C) 30 min
- D) none of these
Q15.A and B can do a work in 4 hours and 12 hours respectively. A starts the work at 6 AM and they work alternately for one hour each. When will the work be completed
- A) 4 days
- B) 5 days
- C) 6 days
- D) 7 days
Q16.When A, B and C are deployed for a task , A and B together do 70% of the work and B and C together do 50% of the work. who is most efficient
- A) A
- B) B
- C) C
- D) can’t be determined
Q17.A tank has an inlet and outlet pipe. The inlet pipe fills the tank completely in 2 hours when the outlet pipe is plugged. The outlet pipe empties the tank completely in 6 hours when the inlet pipe is pluggeed.
If there is a lekage also which is capable of draining out the liquid from the tank at half of the rate of outet pipe,them what is the time taken to fill the emty tank when both the pipes are opened
- A) 3 hours
- B) 4 hours
- C) 5 hours
- D) None of these
Q18.A is twice efficient as B and together they do the same work in as much time as C and D together. If C and D can complete the work in 20 and 30 daysrespectively, working alone ,then in how many days A can complete the work individually
- A) 12 days
- B) 18 days
- C) 24 days
- D) 30 days
Q19.Four pipes A,B, C and D can fill a cistern in 20,25, 40 and 50 hours respectively.The first pipe A was opened at 600 am, B at 800 am, C at 900 am and D at 1000 am. when will the Cistern be full
- A) 418 pm
- B) 309 pm
- C) 1215 pm
- D) 1109 am
Q20.A contractor undertook a project to complete it in 20 days which needed 5 workers to work continuously for all the days estimated. But before the start of the work the client wanted to complete it earlier than the scheduled time, so the contractor calculated that he needed to increase 5 additional men every 2 days to complete the work in the time the client wanted it
If the work was further increased by 50% but the contractor continues to increase the 5 workers o every 2 days then how many more days are required over the initial time specified by the client.
- A) 1 day
- B) 2 days
- C) 5 days
- D) None of these
-:ANSWERS:-
1.Answer B) 300, 200, 250
2.Answer B) 12
3.Answer A) 11 days
4.Answer D) 60 days
5.Answer A) 6011
6.Answer B) 6 days
7.Answer B) 14 27 %
8.Answer D) 10
9.Answer A) 263
10.Answer B) 12 days
11.Answer A) 18 days
12.Answer C) 6
13.Answer C) 247 days
14.Answer B) 54 min
15.Answer C) 6 days
16.Answer A) A
17.Answer B) 4 hours
18.Answer B) 18 days
19.Answer B) 309 pm
20.Answer B) 2 days